Moving faster on the path to Real Zero.
We’re accelerating delivery of the Pilbara Green Grid to bring renewable energy online sooner across our operations.
This means earlier access to large-scale renewable power, earlier reductions in fossil fuel use, and earlier benefits in cost certainty and energy security.
While our Real Zero target remains 2030, this announcement brings forward key milestones, delivering impact sooner, where it matters most.

What we're delivering, when.
What we're delivering, when.
By early FY27 - ~290MW renewable generation
By late FY27 - 24-hour renewable electricity for Pilbara iron ore processing
2028 - Real Zero Green Grid complete
At completion - System capacity at scale
1.5GW solar, 900MW wind, 4–5GWh battery storage. Delivering reliable, dispatchable renewable energy across the Pilbara.
Built for scale across our operations.
A fully integrated system powering the entire Pilbara network.
24 hour
24-hour renewable electricity for Pilbara iron ore processing expected by late FY27.
4–5GWh
In battery storage, enabling dispatchable energy and supporting continuous operations.
1.5GW solar
Large-scale solar generation forming the backbone of the system.
900MW wind
Complementary generation supporting reliability and system balance.